Borders Connection Node A 400kV: grid connection queue
Borders Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lynefield BESS | WINDEL GRID 1 LIMITED | Battery storage | 200 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Lauder | SP Energy Networks | 5.8 km | 4.7 MW | |
| Earlston (Borders) | SP Energy Networks | 7.7 km | 1.6 MW | |
| Gordon | SP Energy Networks | 7.8 km | 3.1 MW | |
| Glendinning Terrace | SP Energy Networks | 13.1 km | 2.1 MW | |
| Netherdale | SP Energy Networks | 13.2 km | 27 MW | 9.3 MW |
| Greenlaw | SP Energy Networks | 13.2 km | 3.9 MW |
Thinking of connecting near Borders Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- LONGCROFT ENERGY PARK 132KV SUBSTATION: 156 MW waiting
- Borders Connection Node A 400kV: 240 MW waiting
- Fallago 400/33kV: 150 MW waiting
- Eccles 400kV: 900 MW waiting
- Eccles 400/132kV: 440 MW waiting