Eccles 400kV: grid connection queue
Eccles 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 900 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 12 Apr 2026 to 30 Apr 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Eccles BESS | Eccles Energy Centre Limited | Battery storage | 500 | 12 Apr 2026 | n/a | Under Construction/Commissioning | 2 | |
| Zenobe Eccles Battery Storage | ZENOBE ECCLES LIMITED | Battery storage | 400 | 30 Apr 2026 | n/a | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 28 Jul 2026 | Eccles BESS | 4 Dec 2026 | 12 Apr 2026 | -8 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Greenlaw | SP Energy Networks | 3.1 km | 3.9 MW | |
| Gordon | SP Energy Networks | 9.1 km | 3.1 MW | |
| Duns | SP Energy Networks | 10.0 km | -21.2 MW | 4.3 MW |
| Oakfield - Kelso | SP Energy Networks | 10.3 km | 21 MW | 15 MW |
| Coldstream | SP Energy Networks | 12.1 km | 1.8 MW | |
| Whitchester | SP Energy Networks | 13.2 km | 3.9 MW |
Thinking of connecting near Eccles 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Eccles 400/132kV: 440 MW waiting
- Eccles: 41 MW waiting
- BISHOPS DAL ENERGY PARK 132kV SUBSTATION: 150 MW waiting
- Kelloe Mains 400kV: 854 MW waiting
- Borders Connection Node A 400kV: 200 MW waiting