Eccles: grid connection queue
Eccles GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 41 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 31 Jul 2031 to 31 Jul 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Coldstream Solar PV Plant | Conrad Energy (Developments) II Limited | Solar | 41 | 31 Jul 2031 | Medium | 31 Jul 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Greenlaw | SP Energy Networks | 3.1 km | 3.9 MW | |
| Gordon | SP Energy Networks | 9.1 km | 3.1 MW | |
| Duns | SP Energy Networks | 10.0 km | -21.2 MW | 4.3 MW |
| Oakfield - Kelso | SP Energy Networks | 10.3 km | 21 MW | 15 MW |
| Coldstream | SP Energy Networks | 12.1 km | 1.8 MW | |
| Whitchester | SP Energy Networks | 13.2 km | 3.9 MW |
Thinking of connecting near Eccles?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Eccles 400kV: 900 MW waiting
- Eccles 400/132kV: 440 MW waiting
- BISHOPS DAL ENERGY PARK 132kV SUBSTATION: 150 MW waiting
- Kelloe Mains 400kV: 854 MW waiting
- Borders Connection Node A 400kV: 200 MW waiting