Kelloe Mains 400kV: grid connection queue
Kelloe Mains 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
3 projects with 854 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 22 Nov 2029 to 30 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kelloe Mains | TBC 003 LIMITED | Battery storage | 400 | 22 Nov 2029 | Medium | 22 Nov 2029 | Scoping | 1 |
| Lees Hill Renewable Energy Park | FRED OLSEN RENEWABLES LIMITED | Mixed and other | 54 | 15 Apr 2033 | Low | 15 Apr 2033 | Scoping | none |
| Edrom Green Energy Park | NP SPV 45 LIMITED | Battery storage | 400 | 30 Oct 2033 | Low | 30 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Duns | SP Energy Networks | 0.9 km | -21.2 MW | 4.3 MW |
| Whitchester | SP Energy Networks | 8.3 km | 3.9 MW | |
| Chirnside | SP Energy Networks | 9.1 km | 22 MW | 8.6 MW |
| Greenlaw | SP Energy Networks | 10.6 km | 3.9 MW | |
| Norham | SP Energy Networks | 13.7 km | 2.8 MW | 1.2 MW |
| Coldstream | SP Energy Networks | 15.3 km | 1.8 MW |
Thinking of connecting near Kelloe Mains 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Eccles 400kV: 900 MW waiting
- Eccles 400/132kV: 440 MW waiting
- Eccles: 41 MW waiting
- BISHOPS DAL ENERGY PARK 132kV SUBSTATION: 150 MW waiting
- Borders Windfarm 132kV: 400 MW waiting