Eccles 400/132kV: grid connection queue

Eccles 400/132kV · SP Transmission (southern Scotland) · register of 26 November 2026

3 projects with 440 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2030.

3projects in the queue
440 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
AMP Eccles BESSEccles Grid Stability LimitedBattery storage5031 Oct 2029Medium31 Oct 2029Scopingnone
Pittlesheugh FarmPittlesheugh Farm BESS LimitedBattery storage34031 Oct 2030Medium31 Oct 2030Scoping1
Coldstream BESSIGP ENERGY STORAGE 4 LIMITEDBattery storage5031 Oct 2030Medium31 Oct 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
GreenlawSP Energy Networks3.1 km3.9 MW
GordonSP Energy Networks9.1 km3.1 MW
DunsSP Energy Networks10.0 km-21.2 MW4.3 MW
Oakfield - KelsoSP Energy Networks10.3 km21 MW15 MW
ColdstreamSP Energy Networks12.1 km1.8 MW
WhitchesterSP Energy Networks13.2 km3.9 MW

Thinking of connecting near Eccles 400/132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points