LONGCROFT ENERGY PARK 132KV SUBSTATION: grid connection queue

LONGCROFT ENERGY PARK 132KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 156 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 May 2031 to 30 May 2031.

1project in the queue
156 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
156 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Longcroft Energy ParkGLENBURNIE ENERGY LIMITEDOnshore wind + storage15630 May 2031High15 Apr 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LauderSP Energy Networks8.7 km4.7 MW
GordonSP Energy Networks16.3 km3.1 MW
PencaitlandSP Energy Networks16.7 km9 MW11 MW
WhitchesterSP Energy Networks17.0 km3.9 MW
Earlston (Borders)SP Energy Networks17.8 km1.6 MW
PeppercraigsSP Energy Networks18.9 km15 MW12 MW

Thinking of connecting near LONGCROFT ENERGY PARK 132KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points