BORDERS SOLAR 132/33KV SUBSTATION: grid connection queue
BORDERS SOLAR 132/33KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 228 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Borders Solar | BUCCLEUCH ESTATES, LTD. (THE) | Solar + storage | 228 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Whitchester | SP Energy Networks | 7.2 km | 3.9 MW | |
| Torness | SP Energy Networks | 13.6 km | 6.5 MW | |
| Spott Road | SP Energy Networks | 14.4 km | 11 MW | 2.2 MW |
| Belhaven Forth | SP Energy Networks | 14.4 km | 11 MW | 0.8 MW |
| East Linton | SP Energy Networks | 15.5 km | 2.2 MW | |
| Duns | SP Energy Networks | 16.1 km | -21.2 MW | 4.3 MW |
Thinking of connecting near BORDERS SOLAR 132/33KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Borders Windfarm 132kV: 400 MW waiting
- Newlands Hill 132/33kV: 119 MW waiting
- Fallago 400/33kV: 150 MW waiting
- Braxbess 400/132kV Collector: 650 MW waiting
- Dunbar 132/33kV: 96 MW waiting