Dunbar 132/33kV: grid connection queue
Dunbar 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 96 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Jul 2032 to 31 Jul 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Pitcox BESS | ABEI ENERGY LIMITED | Battery storage | 96 | 31 Jul 2032 | Low | 31 Jul 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Belhaven Forth | SP Energy Networks | 3.4 km | 11 MW | 0.8 MW |
| Spott Road | SP Energy Networks | 4.4 km | 11 MW | 2.2 MW |
| East Linton | SP Energy Networks | 6.7 km | 2.2 MW | |
| Torness | SP Energy Networks | 9.4 km | 6.5 MW | |
| Peppercraigs | SP Energy Networks | 14.2 km | 15 MW | 12 MW |
| North Berwick | SP Energy Networks | 14.5 km | 26 MW | 7.9 MW |
Thinking of connecting near Dunbar 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Branxton 400/132kV: 1,167 MW waiting
- Braxbess 400/132kV Collector: 650 MW waiting
- Torness 400/132kV: 150 MW waiting
- Branxton 400kV: 3,510 MW waiting
- Near Branxton 400kV: 2,900 MW waiting