Branxton 400kV: grid connection queue

Branxton 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

3 projects with 3,510 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2029.

3projects in the queue
3,510 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
1,380 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Berwick Bank Offshore Wind Farm ABERWICK BANK A LIMITEDOffshore wind1,38031 Oct 2028High15 Nov 2030Scopingnone
Branxton Energy Storage FacilityEastCoastGridServices LtdBattery storage75013 May 2029Medium13 May 2029Scopingnone
Berwick Bank Offshore Wind Farm BBerwick Bank B LimitedOffshore wind1,38031 Oct 2029Medium31 Oct 2029Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
TornessSP Energy Networks1.9 km6.5 MW
Spott RoadSP Energy Networks7.9 km11 MW2.2 MW
Belhaven ForthSP Energy Networks9.4 km11 MW0.8 MW
WhitchesterSP Energy Networks15.2 km3.9 MW
East LintonSP Energy Networks16.5 km2.2 MW
DunsSP Energy Networks19.8 km-21.2 MW4.3 MW

Thinking of connecting near Branxton 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points