Near Branxton 400kV: grid connection queue
Near Branxton 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 2,900 MW are waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 30 Jun 2032 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| INTOG 2 | CERULEAN WINDS LIMITED | Offshore wind | 1,400 | 30 Jun 2032 | Low | 30 Jun 2032 | Scoping | none |
| Phoenix 1B Offshore Wind Farm | Morven Offshore Wind Limited | Offshore wind | 1,500 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Torness | SP Energy Networks | 1.9 km | 6.5 MW | |
| Spott Road | SP Energy Networks | 7.9 km | 11 MW | 2.2 MW |
| Belhaven Forth | SP Energy Networks | 9.4 km | 11 MW | 0.8 MW |
| Whitchester | SP Energy Networks | 15.2 km | 3.9 MW | |
| East Linton | SP Energy Networks | 16.5 km | 2.2 MW | |
| Duns | SP Energy Networks | 19.8 km | -21.2 MW | 4.3 MW |
Thinking of connecting near Near Branxton 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Branxton 400kV: 3,510 MW waiting
- Thorntonloch 400kV: 240 MW waiting
- Torness 400/132kV: 150 MW waiting
- Braxbess 400/132kV Collector: 650 MW waiting
- Dunbar 132/33kV: 96 MW waiting