Branxton 400/132kV: grid connection queue
Branxton 400/132kV · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 1,167 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Branxton PV & BESS Station | IGP Solar 26 Limited | Battery storage | 1,000 | 31 Oct 2028 | High | 31 Oct 2030 | Scoping | 1 |
| Springfield Solar and Battery | VOLTALIA UK LTD | Solar + storage | 167 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Belhaven Forth | SP Energy Networks | 1.0 km | 11 MW | 0.8 MW |
| Spott Road | SP Energy Networks | 2.7 km | 11 MW | 2.2 MW |
| East Linton | SP Energy Networks | 7.2 km | 2.2 MW | |
| Torness | SP Energy Networks | 9.3 km | 6.5 MW | |
| North Berwick | SP Energy Networks | 13.6 km | 26 MW | 7.9 MW |
| Peppercraigs | SP Energy Networks | 15.2 km | 15 MW | 12 MW |
Thinking of connecting near Branxton 400/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Dunbar 132/33kV: 96 MW waiting
- Braxbess 400/132kV Collector: 650 MW waiting
- Torness 400/132kV: 150 MW waiting
- Thorntonloch 400kV: 240 MW waiting
- Branxton 400kV: 3,510 MW waiting