Cockenzie 400/275kV: grid connection queue
Cockenzie 400/275kV · SP Transmission (southern Scotland) · register of 26 November 2026
3 projects with 1,340 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 21 Feb 2026 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Inch Cape Offshore Wind Farm Platform 1 | INCH CAPE OFFSHORE LIMITED | Offshore wind | 540 | 21 Feb 2026 | n/a | Under Construction/Commissioning | 2 | |
| Seagreen 1A Offshore Wind Farm | SEAGREEN 1A LIMITED | Offshore wind | 500 | 1 Apr 2028 | High | 16 Apr 2030 | Under Construction/Commissioning | none |
| Boom Power Seaton Hill Generation HUB | Seatonhill Storage Facility Limited | Battery storage | 300 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Pencaitland | SP Energy Networks | 3.8 km | 9 MW | 11 MW |
| Peppercraigs | SP Energy Networks | 6.4 km | 15 MW | 12 MW |
| Tranent | SP Energy Networks | 8.6 km | 28 MW | 3.9 MW |
| Prestonpans | SP Energy Networks | 9.7 km | 26 MW | 13 MW |
| East Linton | SP Energy Networks | 13.5 km | 2.2 MW | |
| Monktonhall | SP Energy Networks | 13.8 km | 27 MW | 8.8 MW |
Thinking of connecting near Cockenzie 400/275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Cockenzie 275kV substation: 540 MW waiting
- Cockenzie 275/33kV: 63 MW waiting
- Meadowmill 400/132kV: 342 MW waiting
- Fallago 400/33kV: 150 MW waiting
- Newlands Hill 132/33kV: 119 MW waiting