Ferrybridge B 132kV: grid connection queue
Ferrybridge B 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 300 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 24 Oct 2035 to 30 Oct 2035.
2projects in the queue
300 MWwaiting to connect
150 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ferrybridge B BESS & Solar Substation | O&G Solar (SPV 19) Limited | Solar + storage | 100 | 24 Oct 2035 | Low | 24 Oct 2035 | Consents Approved | none |
| NEL Tiger | UE 1 LTD | Battery storage | 200 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Ferrybridge B 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Monk Fryston 400kV: 1,700 MW waiting
- Monk Fryston 275kV: 970 MW waiting
- Leeds North Connection Node A 400kV: 200 MW waiting
- Ferrybridge C 275kV: 1,670 MW waiting
- Leeds North Connection Node G: 200 MW waiting