Rowan 275/33kV: grid connection queue

Rowan 275/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 91 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

1project in the queue
91 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Rowan Wind EnergyfarmENERGYFARM ROWAN LLPOnshore wind + storage9131 Oct 2034Low31 Oct 2034Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Rowan 275/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.