CRAIG WATCH WIND FARM 132KV SUBSTATION: grid connection queue
CRAIG WATCH WIND FARM 132KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 73 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 15 May 2031 to 15 May 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Craig Watch Wind Farm | Craig Watch Wind Farm Limited | Onshore wind | 73 | 15 May 2031 | High | 31 Mar 2033 | Awaiting Consents | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Dufftown Primary | SSEN Distribution | 0.4 km | 0 MW | 0.1 MW |
| Aberlour Primary | SSEN Distribution | 7.5 km | 0 MW | 0 MW |
| Rothes Primary | SSEN Distribution | 10.6 km | 0 MW | 0.5 MW |
| Glenfarclas GSP | SSEN Distribution | 11.7 km | ||
| Ballindalloch Primary | SSEN Distribution | 14.1 km | 0 MW | 6.6 MW |
| Keith Primary | SSEN Distribution | 15.6 km | 0 MW | 6.4 MW |
Thinking of connecting near CRAIG WATCH WIND FARM 132KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Teindland 132/33KV Wind Farm: 112 MW waiting
- Dorenell Extension Wind Farm 400kV: 610 MW waiting
- Dorenell BESS 132KV substation: 38 MW waiting
- Keith Solar Farm 275kV: 150 MW waiting
- Keith 2 132/33kV GSP: 132 MW waiting