Keith 2 132/33kV GSP: grid connection queue
Keith 2 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
3 projects with 132 MW are waiting to connect here (largest by capacity: onshore wind, battery storage). Contracted dates run from 31 Oct 2026 to 1 Jun 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Drum Farm Energy Storage Facility | Field Drum Farm Ltd | Battery storage | 50 | 31 Oct 2026 | n/a | Consents Approved | 2 | |
| Garbet Wind Farm | GARBET WIND FARM LLP | Onshore wind | 46 | 31 Oct 2026 | n/a | Consents Approved | 2 | |
| Hill of Towie 2 Wind Farm | GREENHILLS 1 LIMITED | Onshore wind | 36 | 1 Jun 2030 | High | 17 Apr 2032 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 22 Sep 2026 | Drum Farm Energy Storage Facility | 31 Oct 2028 | 31 Oct 2026 | -24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cairnford GSP | SSEN Distribution | 5.3 km | ||
| Keith Primary | SSEN Distribution | 6.8 km | 0 MW | 6.4 MW |
| Keith 2 GSP | SSEN Distribution | 6.9 km | ||
| Keith 1 GSP | SSEN Distribution | 6.9 km | ||
| Huntly Primary | SSEN Distribution | 9.1 km | 0 MW | 8.1 MW |
| Limehillocks Primary | SSEN Distribution | 10.2 km | 0 MW | 0 MW |
Thinking of connecting near Keith 2 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Keith Solar Farm 275kV: 150 MW waiting
- Keith 132kV: 48 MW waiting
- Keith 1 132/33kV GSP: 39 MW waiting
- New North East 275kV: 200 MW waiting
- Blackhillock substation: 400 MW waiting