Benzene

Keith 2 132/33kV GSP: grid connection queue

Keith 2 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

3 projects with 132 MW are waiting to connect here (largest by capacity: onshore wind, battery storage). Contracted dates run from 31 Oct 2026 to 1 Jun 2030.

3projects in the queue
132 MWwaiting to connect
0 MWalready connected
132 MWholding Gate 2
1date moves since 2 Jun 2026
36 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Drum Farm Energy Storage FacilityField Drum Farm LtdBattery storage5031 Oct 2026n/aConsents Approved2
Garbet Wind FarmGARBET WIND FARM LLPOnshore wind4631 Oct 2026n/aConsents Approved2
Hill of Towie 2 Wind FarmGREENHILLS 1 LIMITEDOnshore wind361 Jun 2030High17 Apr 2032Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
22 Sep 2026Drum Farm Energy Storage Facility31 Oct 202831 Oct 2026-24 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cairnford GSPSSEN Distribution5.3 km
Keith PrimarySSEN Distribution6.8 km0 MW6.4 MW
Keith 2 GSPSSEN Distribution6.9 km
Keith 1 GSPSSEN Distribution6.9 km
Huntly PrimarySSEN Distribution9.1 km0 MW8.1 MW
Limehillocks PrimarySSEN Distribution10.2 km0 MW0 MW

Thinking of connecting near Keith 2 132/33kV GSP?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.