Benzene

Blackhillock substation: grid connection queue

Blackhillock substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 400 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.

1project in the queue
400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Keith BESS StationIBV COACHFORD ENERGY PARK LTDBattery storage40031 Oct 2033Low31 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cairnford GSPSSEN Distribution5.4 km
Keith PrimarySSEN Distribution5.9 km0 MW6.4 MW
Keith 2 GSPSSEN Distribution5.9 km
Keith 1 GSPSSEN Distribution6.0 km
Limehillocks PrimarySSEN Distribution8.6 km0 MW0 MW
Huntly PrimarySSEN Distribution8.9 km0 MW8.1 MW

Thinking of connecting near Blackhillock substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points