Blackhillock 400kV: grid connection queue

Blackhillock 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 349 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.

1project in the queue
349 MWwaiting to connect
0 MWalready connected
349 MWholding Gate 2
1date moves since 2 Jun 2026
349 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Blackhillock BatteryBLACKHILLOCK FLEXPOWER LTDBattery storage34931 Oct 2028High31 Oct 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
16 Jun 2026Blackhillock Battery31 Oct 202731 Oct 2028+12 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Cairnford GSPSSEN Distribution5.4 km
Keith PrimarySSEN Distribution5.9 km0 MW6.4 MW
Keith 2 GSPSSEN Distribution5.9 km
Keith 1 GSPSSEN Distribution6.0 km
Limehillocks PrimarySSEN Distribution8.6 km0 MW0 MW
Huntly PrimarySSEN Distribution8.9 km0 MW8.1 MW

Thinking of connecting near Blackhillock 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.