New North East 275kV: grid connection queue
New North East 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ardonald Wind Farm | Ardonald Renewables Limited | Mixed and other | 200 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cairnford GSP | SSEN Distribution | 5.0 km | ||
| Keith Primary | SSEN Distribution | 6.8 km | 0 MW | 6.4 MW |
| Keith 2 GSP | SSEN Distribution | 6.8 km | ||
| Keith 1 GSP | SSEN Distribution | 6.9 km | ||
| Huntly Primary | SSEN Distribution | 8.8 km | 0 MW | 8.1 MW |
| Limehillocks Primary | SSEN Distribution | 9.8 km | 0 MW | 0 MW |
Thinking of connecting near New North East 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Keith Solar Farm 275kV: 150 MW waiting
- Keith 2 132/33kV GSP: 132 MW waiting
- Keith 132kV: 48 MW waiting
- Keith 1 132/33kV GSP: 39 MW waiting
- Blackhillock substation: 400 MW waiting