Keith 132kV: grid connection queue
Keith 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 48 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 1 Apr 2029 to 1 Apr 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Keith 132 Greener Grid Park | KEITH STORAGE SOLUTIONS LIMITED | Battery storage | 48 | 1 Apr 2029 | Medium | 1 Apr 2029 | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 4 Aug 2026 | Keith 132 Greener Grid Park | 31 May 2025 | 1 Apr 2029 | +46 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cairnford GSP | SSEN Distribution | 5.3 km | ||
| Keith Primary | SSEN Distribution | 6.8 km | 0 MW | 6.4 MW |
| Keith 2 GSP | SSEN Distribution | 6.9 km | ||
| Keith 1 GSP | SSEN Distribution | 6.9 km | ||
| Huntly Primary | SSEN Distribution | 9.1 km | 0 MW | 8.1 MW |
| Limehillocks Primary | SSEN Distribution | 10.2 km | 0 MW | 0 MW |
Thinking of connecting near Keith 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Keith Solar Farm 275kV: 150 MW waiting
- Keith 2 132/33kV GSP: 132 MW waiting
- Keith 1 132/33kV GSP: 39 MW waiting
- New North East 275kV: 200 MW waiting
- Blackhillock substation: 400 MW waiting