Teindland 132/33KV Wind Farm: grid connection queue

Teindland 132/33KV Wind Farm Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 112 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 28 Sep 2029 to 28 Sep 2029.

1project in the queue
112 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
112 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Teindland Wind FarmTEINDLAND WIND FARM LIMITEDOnshore wind11228 Sep 2029High15 Aug 2031Awaiting Consents1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Rothes PrimarySSEN Distribution0.6 km0 MW0.5 MW
Aberlour PrimarySSEN Distribution8.8 km0 MW0 MW
Dufftown PrimarySSEN Distribution10.3 km0 MW0.1 MW
Fochabers PrimarySSEN Distribution12.1 km0 MW0 MW
Lhanbryde PrimarySSEN Distribution12.5 km0 MW0 MW
Dallas GSPSSEN Distribution13.2 km

Thinking of connecting near Teindland 132/33KV Wind Farm?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points