Elgin: grid connection queue

Elgin GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 30 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.

1project in the queue
30 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
30 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Elgin BESSGPC 612 LtdBattery storage3031 Oct 2028High31 Oct 2030Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Ashgrove PrimarySSEN Distribution1.0 km0 MW0 MW
Cumming Street PrimarySSEN Distribution2.0 km0 MW7.5 MW
Bilbohall PrimarySSEN Distribution2.8 km0 MW7 MW
Elgin GSPSSEN Distribution3.2 km
Elgin PrimarySSEN Distribution3.2 km0 MW7.2 MW
Lhanbryde PrimarySSEN Distribution4.5 km0 MW0 MW

Thinking of connecting near Elgin?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points