Aultmore Wind Farm 132/33kV: grid connection queue
Aultmore Wind Farm 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 105 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Sep 2030 to 30 Sep 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Aultmore Wind Farm (2023) | VATTENFALL WIND POWER LTD | Onshore wind + storage | 105 | 30 Sep 2030 | High | 16 Aug 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Keith 1 GSP | SSEN Distribution | 3.9 km | ||
| Keith 2 GSP | SSEN Distribution | 3.9 km | ||
| Keith Primary | SSEN Distribution | 4.0 km | 0 MW | 6.4 MW |
| Limehillocks Primary | SSEN Distribution | 8.6 km | 0 MW | 0 MW |
| Buckie Primary | SSEN Distribution | 10.5 km | 0 MW | 0 MW |
| Fochabers Primary | SSEN Distribution | 11.7 km | 0 MW | 0 MW |
Thinking of connecting near Aultmore Wind Farm 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Blackhillock substation: 400 MW waiting
- Blackhillock 400kV: 349 MW waiting
- Blackhillock 275kV: 250 MW waiting
- New North East 275kV: 200 MW waiting
- Keith Solar Farm 275kV: 150 MW waiting