Benzene

Clash Gour Wind Farm 132kV: grid connection queue

Clash Gour Wind Farm 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 210 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Oct 2029 to 30 Oct 2029.

1project in the queue
210 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
210 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Clash GourCLASH GOUR WINDFARM HOLDINGS LIMITEDOnshore wind + storage21030 Oct 2029High16 Sep 2031Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Berryburn GSPSSEN Distribution4.4 km
Dallas GSPSSEN Distribution10.6 km
Ballindalloch PrimarySSEN Distribution15.2 km0 MW6.6 MW
Glenfarclas GSPSSEN Distribution15.2 km
Forres PrimarySSEN Distribution15.3 km0 MW0 MW
Lethen PrimarySSEN Distribution16.8 km0 MW0 MW

Thinking of connecting near Clash Gour Wind Farm 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points