Lethen Wind Farm 132/33kV: grid connection queue
Lethen Wind Farm 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 114 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Dec 2033 to 1 Dec 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lethen Wind Farm | FRED OLSEN RENEWABLES LIMITED | Onshore wind | 114 | 1 Dec 2033 | Low | 1 Dec 2033 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Lethen Wind Farm | 31 Dec 2033 | 1 Dec 2033 | -1 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Grantown Primary | SSEN Distribution | 14.1 km | 0 MW | 8.1 MW |
| Lethen Primary | SSEN Distribution | 15.1 km | 0 MW | 0 MW |
| Tomatin Primary | SSEN Distribution | 15.3 km | 0 MW | 0 MW |
| Berryburn GSP | SSEN Distribution | 15.9 km | ||
| Boat of Garten GSP | SSEN Distribution | 16.5 km | ||
| Boat of Garten Primary | SSEN Distribution | 16.5 km | 0 MW | 7.2 MW |
Thinking of connecting near Lethen Wind Farm 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Nairn 132/33kV Grid Supply Point: 50 MW waiting
- Balnespick Wind Farm 132kV/33kV: 58 MW waiting
- Berryburn 275/33kV GSP: 160 MW waiting
- Ourack 132/33kV: 105 MW waiting
- Tomatin 132kV Substation Extension: 91 MW waiting