Lethen Wind Farm 132/33kV: grid connection queue

Lethen Wind Farm 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 114 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Dec 2033 to 1 Dec 2033.

1project in the queue
114 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lethen Wind FarmFRED OLSEN RENEWABLES LIMITEDOnshore wind1141 Dec 2033Low1 Dec 2033Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Lethen Wind Farm31 Dec 20331 Dec 2033-1 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Grantown PrimarySSEN Distribution14.1 km0 MW8.1 MW
Lethen PrimarySSEN Distribution15.1 km0 MW0 MW
Tomatin PrimarySSEN Distribution15.3 km0 MW0 MW
Berryburn GSPSSEN Distribution15.9 km
Boat of Garten GSPSSEN Distribution16.5 km
Boat of Garten PrimarySSEN Distribution16.5 km0 MW7.2 MW

Thinking of connecting near Lethen Wind Farm 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points