Nairn 132/33kV Grid Supply Point: grid connection queue
Nairn 132/33kV Grid Supply Point Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Jan 2028 to 31 Jan 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Newton of Park BESS 2 | Opdenergy UK 16 Limited | Battery storage | 50 | 31 Jan 2028 | High | 30 Jan 2030 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Grantown Primary | SSEN Distribution | 10.0 km | 0 MW | 8.1 MW |
| Boat of Garten GSP | SSEN Distribution | 10.5 km | ||
| Boat of Garten Primary | SSEN Distribution | 10.5 km | 0 MW | 7.2 MW |
| Tomatin Primary | SSEN Distribution | 15.2 km | 0 MW | 0 MW |
| Aviemore Primary | SSEN Distribution | 19.0 km | 0 MW | 1.3 MW |
| Berryburn GSP | SSEN Distribution | 19.9 km |
Thinking of connecting near Nairn 132/33kV Grid Supply Point?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Lethen Wind Farm 132/33kV: 114 MW waiting
- Balnespick Wind Farm 132kV/33kV: 58 MW waiting
- Ourack 132/33kV: 105 MW waiting
- Tomatin 132kV Substation Extension: 91 MW waiting
- Lynemore Windfarm 132kV: 84 MW waiting