Ourack 132/33kV: grid connection queue

Ourack 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 105 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Mar 2032 to 31 Mar 2032.

1project in the queue
105 MWwaiting to connect
0 MWalready connected
105 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Ourack Wind FarmOURACK WIND FARM LLPOnshore wind + storage10531 Mar 2032Low31 Mar 2032Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
10 Nov 2026Ourack Wind Farm31 Oct 203031 Mar 2032+17 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Berryburn GSPSSEN Distribution8.3 km
Grantown PrimarySSEN Distribution12.6 km0 MW8.1 MW
Ballindalloch PrimarySSEN Distribution14.9 km0 MW6.6 MW
Glenfarclas GSPSSEN Distribution16.2 km
Dallas GSPSSEN Distribution17.2 km
Lethen PrimarySSEN Distribution17.4 km0 MW0 MW

Thinking of connecting near Ourack 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points