Ourack 132/33kV: grid connection queue
Ourack 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 105 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Mar 2032 to 31 Mar 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ourack Wind Farm | OURACK WIND FARM LLP | Onshore wind + storage | 105 | 31 Mar 2032 | Low | 31 Mar 2032 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 10 Nov 2026 | Ourack Wind Farm | 31 Oct 2030 | 31 Mar 2032 | +17 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Berryburn GSP | SSEN Distribution | 8.3 km | ||
| Grantown Primary | SSEN Distribution | 12.6 km | 0 MW | 8.1 MW |
| Ballindalloch Primary | SSEN Distribution | 14.9 km | 0 MW | 6.6 MW |
| Glenfarclas GSP | SSEN Distribution | 16.2 km | ||
| Dallas GSP | SSEN Distribution | 17.2 km | ||
| Lethen Primary | SSEN Distribution | 17.4 km | 0 MW | 0 MW |
Thinking of connecting near Ourack 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Berryburn 275/33kV GSP: 160 MW waiting
- Clash Gour Wind Farm 132kV: 210 MW waiting
- Lethen Wind Farm 132/33kV: 114 MW waiting
- Nairn 132/33kV Grid Supply Point: 50 MW waiting
- Kellas Wind Farm 132kV: 90 MW waiting