Berryburn 275/33kV GSP: grid connection queue

Berryburn 275/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

3 projects with 160 MW are waiting to connect here (largest by capacity: onshore wind, battery storage). Contracted dates run from 31 Oct 2027 to 31 Oct 2028.

3projects in the queue
160 MWwaiting to connect
0 MWalready connected
160 MWholding Gate 2
3date moves since 2 Jun 2026
160 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Berryburn Extension Wind FarmBB2 WIND FARM LIMITEDOnshore wind4331 Oct 2027High28 Dec 2029Consents Approved2
Cairn Duhie Wind FarmCAIRN DUHIE ENERGY LIMITEDOnshore wind6731 Oct 2028High29 Dec 2030Consents Approved2
Corshellach Battery Energy Storage SystemCorshellach Energy Storage LimitedBattery storage5031 Oct 2028High31 Oct 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 3 times: 3 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
1 Sep 2026Corshellach Battery Energy Storage System31 Oct 202731 Oct 2028+12 months
18 Aug 2026Cairn Duhie Wind Farm31 Oct 202731 Oct 2028+12 months
11 Aug 2026Berryburn Extension Wind Farm30 Nov 202531 Oct 2027+23 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Berryburn GSPSSEN Distribution3.7 km
Lethen PrimarySSEN Distribution11.7 km0 MW0 MW
Forres PrimarySSEN Distribution15.3 km0 MW0 MW
Dallas GSPSSEN Distribution15.7 km
Nairn GSPSSEN Distribution16.8 km
Grantown PrimarySSEN Distribution18.0 km0 MW8.1 MW

Thinking of connecting near Berryburn 275/33kV GSP?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points