Longmorn Energy Park 275kV: grid connection queue
Longmorn Energy Park 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 300 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 15 Aug 2031 to 15 Aug 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Longmorn Energy Park | ELGIN ENERGY ES CO LIMITED | Solar + storage | 300 | 15 Aug 2031 | Medium | 15 Aug 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ashgrove Primary | SSEN Distribution | 5.1 km | 0 MW | 0 MW |
| Bilbohall Primary | SSEN Distribution | 5.2 km | 0 MW | 7 MW |
| Cumming Street Primary | SSEN Distribution | 6.2 km | 0 MW | 7.5 MW |
| Lhanbryde Primary | SSEN Distribution | 6.3 km | 0 MW | 0 MW |
| Elgin GSP | SSEN Distribution | 7.9 km | ||
| Elgin Primary | SSEN Distribution | 7.9 km | 0 MW | 7.2 MW |
Thinking of connecting near Longmorn Energy Park 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Elgin: 30 MW waiting
- Kellas Wind Farm 132kV: 90 MW waiting
- Teindland 132/33KV Wind Farm: 112 MW waiting
- CRAIG WATCH WIND FARM 132KV SUBSTATION: 73 MW waiting
- Clash Gour Wind Farm 132kV: 210 MW waiting