Overton 275kV: grid connection queue

Overton 275kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 2,425 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 1 Jun 2032 to 24 Oct 2035.

2projects in the queue
2,425 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Overton Solar & Storage FarmELEMENTS GREEN LIMITEDSolar + storage1,4001 Jun 2032Low1 Jun 2032Scoping1
Overton Green Energy CentreOVERTON NG LIMITEDSolar + storage1,02524 Oct 2035Low24 Oct 2035Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Overton PrimarySSEN Distribution1.4 km0 MW32 MW
Whitchurch PrimarySSEN Distribution5.2 km0 MW1.4 MW
Kingsclere PrimarySSEN Distribution9.1 km0 MW4.1 MW
Down Grange PrimarySSEN Distribution10.8 km0 MW11 MW
Barton Stacey PrimarySSEN Distribution11.5 km0 MW12 MW
Hurstbourne Tarrant PrimarySSEN Distribution11.6 km0 MW1.7 MW

Thinking of connecting near Overton 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.