Bramley: grid connection queue
Bramley · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 480 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Pamber Farm | Queequeg Renewables Ltd | Battery storage | 480 | 31 Oct 2037 | Low | 31 Oct 2037 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Basingstoke Primary | SSEN Distribution | 1.3 km | 0 MW | 16 MW |
| Basingstoke (T3 & T4) BSP | SSEN Distribution | 1.3 km | 0 MW | 55 MW |
| Basingstoke (T1B & T2B) BSP | SSEN Distribution | 1.3 km | 0 MW | 46 MW |
| Basingstoke (T1A & T2A) BSP | SSEN Distribution | 1.3 km | 0 MW | 27 MW |
| Brook Street Primary | SSEN Distribution | 3.0 km | 0 MW | 15 MW |
| Oarkridge Primary | SSEN Distribution | 3.1 km | 0 MW | 16 MW |
Thinking of connecting near Bramley?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Fleet 400kV: 200 MW waiting
- Bramley 400kV: 114 MW waiting
- Basingstoke East 400kV: 1,800 MW waiting
- Overton 275kV: 2,425 MW waiting
- Nursling 400kV: 2,980 MW waiting