Bramley 400kV: grid connection queue
Bramley 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 114 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2027 to 30 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bramley BESS | BRAMLEY BESS LIMITED | Battery storage | 57 | 30 Oct 2027 | High | 29 Oct 2029 | Under Construction/Commissioning | 2 |
| Bramley (tertiary) | BRAMLEY SOLAR LIMITED | Solar + storage | 57 | 30 Oct 2027 | High | 29 Oct 2029 | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 11 Aug 2026 | Bramley BESS | 29 Sep 2025 | 30 Oct 2027 | +25 months |
| 11 Aug 2026 | Bramley (tertiary) | 16 Aug 2026 | 30 Oct 2027 | +14 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Basingstoke Primary | SSEN Distribution | 1.3 km | 0 MW | 16 MW |
| Basingstoke (T3 & T4) BSP | SSEN Distribution | 1.3 km | 0 MW | 55 MW |
| Basingstoke (T1B & T2B) BSP | SSEN Distribution | 1.3 km | 0 MW | 46 MW |
| Basingstoke (T1A & T2A) BSP | SSEN Distribution | 1.3 km | 0 MW | 27 MW |
| Brook Street Primary | SSEN Distribution | 3.0 km | 0 MW | 15 MW |
| Oarkridge Primary | SSEN Distribution | 3.1 km | 0 MW | 16 MW |
Thinking of connecting near Bramley 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bramley: 480 MW waiting
- Fleet 400kV: 200 MW waiting
- Basingstoke East 400kV: 1,800 MW waiting
- Overton 275kV: 2,425 MW waiting
- Nursling 400kV: 2,980 MW waiting