Bramley 400kV: grid connection queue

Bramley 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 114 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2027 to 30 Oct 2027.

2projects in the queue
114 MWwaiting to connect
47 MWalready connected
114 MWholding Gate 2
2date moves since 2 Jun 2026
114 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bramley BESSBRAMLEY BESS LIMITEDBattery storage5730 Oct 2027High29 Oct 2029Under Construction/Commissioning2
Bramley (tertiary)BRAMLEY SOLAR LIMITEDSolar + storage5730 Oct 2027High29 Oct 2029Under Construction/Commissioning2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
11 Aug 2026Bramley BESS29 Sep 202530 Oct 2027+25 months
11 Aug 2026Bramley (tertiary)16 Aug 202630 Oct 2027+14 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Basingstoke PrimarySSEN Distribution1.3 km0 MW16 MW
Basingstoke (T3 & T4) BSPSSEN Distribution1.3 km0 MW55 MW
Basingstoke (T1B & T2B) BSPSSEN Distribution1.3 km0 MW46 MW
Basingstoke (T1A & T2A) BSPSSEN Distribution1.3 km0 MW27 MW
Brook Street PrimarySSEN Distribution3.0 km0 MW15 MW
Oarkridge PrimarySSEN Distribution3.1 km0 MW16 MW

Thinking of connecting near Bramley 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points