Basingstoke East 400kV: grid connection queue
Basingstoke East 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,800 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Mar 2038 to 30 Jun 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bramley Farm | BRAMLEY 2 RENEWABLES LTD | Solar + storage | 200 | 30 Mar 2038 | Low | 30 Mar 2038 | Scoping | 1 |
| Fleet Farm | BASINGSTOKE EAST 2 RENEWABLES LTD | Solar + storage | 200 | 30 Apr 2038 | Low | 30 Apr 2038 | Scoping | 1 |
| Bramley Farm 2 | BRAMLEY 7 RENEWABLES LTD | Solar + storage | 700 | 30 May 2038 | Low | 30 May 2038 | Scoping | 1 |
| Fleet Farm 2 | Basingstoke East 7 Renewables Ltd | Solar + storage | 700 | 30 Jun 2038 | Low | 30 Jun 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Basingstoke (T3 & T4) BSP | SSEN Distribution | 0.5 km | 0 MW | 55 MW |
| Basingstoke (T1B & T2B) BSP | SSEN Distribution | 0.5 km | 0 MW | 46 MW |
| Basingstoke (T1A & T2A) BSP | SSEN Distribution | 0.5 km | 0 MW | 27 MW |
| Basingstoke Primary | SSEN Distribution | 0.6 km | 0 MW | 16 MW |
| Oarkridge Primary | SSEN Distribution | 1.4 km | 0 MW | 16 MW |
| Brook Street Primary | SSEN Distribution | 1.4 km | 0 MW | 15 MW |
Thinking of connecting near Basingstoke East 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bramley: 480 MW waiting
- Fleet 400kV: 200 MW waiting
- Bramley 400kV: 114 MW waiting
- Overton 275kV: 2,425 MW waiting
- Nursling 400kV: 2,980 MW waiting