Fleet 400kV: grid connection queue
Fleet 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 200 MW are waiting to connect here (largest by capacity: solar, solar + storage). Contracted dates run from 13 Jan 2027 to 30 Jul 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Fleet EGH (Tertiary) | FLEET GREEN LIMITED | Solar + storage | 48 | 13 Jan 2027 | High | 12 Jan 2029 | Consents Approved | none |
| Fleet Solar PV | FLEET SOLAR LIMITED | Solar | 57 | 7 Aug 2028 | High | 22 Aug 2030 | Awaiting Consents | none |
| Fleet Tertiary | FLEET SOLAR LIMITED | Gas and thermal | 48 | 7 Aug 2028 | High | 22 Mar 2031 | Scoping | 1 |
| Fleet (Tertiary) | CSE23 LIMITED | Solar | 48 | 30 Jul 2029 | Medium | 30 Jul 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 6 Oct 2026 | Fleet (Tertiary) | 31 Oct 2026 | 30 Jul 2029 | +33 months |
| 11 Aug 2026 | Fleet Tertiary | 30 Nov 2025 | 7 Aug 2028 | +32 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Basingstoke Primary | SSEN Distribution | 1.3 km | 0 MW | 16 MW |
| Basingstoke (T3 & T4) BSP | SSEN Distribution | 1.3 km | 0 MW | 55 MW |
| Basingstoke (T1B & T2B) BSP | SSEN Distribution | 1.3 km | 0 MW | 46 MW |
| Basingstoke (T1A & T2A) BSP | SSEN Distribution | 1.3 km | 0 MW | 27 MW |
| Brook Street Primary | SSEN Distribution | 3.0 km | 0 MW | 15 MW |
| Oarkridge Primary | SSEN Distribution | 3.1 km | 0 MW | 16 MW |
Thinking of connecting near Fleet 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bramley: 480 MW waiting
- Bramley 400kV: 114 MW waiting
- Basingstoke East 400kV: 1,800 MW waiting
- Overton 275kV: 2,425 MW waiting
- Nursling 400kV: 2,980 MW waiting