Fleet 400kV: grid connection queue

Fleet 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 200 MW are waiting to connect here (largest by capacity: solar, solar + storage). Contracted dates run from 13 Jan 2027 to 30 Jul 2029.

4projects in the queue
200 MWwaiting to connect
0 MWalready connected
48 MWholding Gate 2
2date moves since 2 Jun 2026
152 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Fleet EGH (Tertiary)FLEET GREEN LIMITEDSolar + storage4813 Jan 2027High12 Jan 2029Consents Approvednone
Fleet Solar PVFLEET SOLAR LIMITEDSolar577 Aug 2028High22 Aug 2030Awaiting Consentsnone
Fleet TertiaryFLEET SOLAR LIMITEDGas and thermal487 Aug 2028High22 Mar 2031Scoping1
Fleet (Tertiary)CSE23 LIMITEDSolar4830 Jul 2029Medium30 Jul 2029Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
6 Oct 2026Fleet (Tertiary)31 Oct 202630 Jul 2029+33 months
11 Aug 2026Fleet Tertiary30 Nov 20257 Aug 2028+32 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Basingstoke PrimarySSEN Distribution1.3 km0 MW16 MW
Basingstoke (T3 & T4) BSPSSEN Distribution1.3 km0 MW55 MW
Basingstoke (T1B & T2B) BSPSSEN Distribution1.3 km0 MW46 MW
Basingstoke (T1A & T2A) BSPSSEN Distribution1.3 km0 MW27 MW
Brook Street PrimarySSEN Distribution3.0 km0 MW15 MW
Oarkridge PrimarySSEN Distribution3.1 km0 MW16 MW

Thinking of connecting near Fleet 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points