Benzene

New East Coast 400kV: grid connection queue

New East Coast 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 1,000 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.

1project in the queue
1,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Halfway Energy ParkDALRIADA RENEWABLES LIMITEDSolar + storage1,00031 Oct 2035Low31 Oct 2035Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Craigiebuckler PrimarySSEN Distribution0.4 km0 MW3.6 MW
Craigiebuckler GSPSSEN Distribution0.4 km
Ruthrieston PrimarySSEN Distribution1.5 km0 MW3.6 MW
Queens Lane North PrimarySSEN Distribution1.6 km13 MW2.4 MW
Springhill PrimarySSEN Distribution2.3 km22 MW0 MW
Craigton PrimarySSEN Distribution2.3 km0 MW3.6 MW

Thinking of connecting near New East Coast 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points