Gills Bay 132kV: grid connection queue
Gills Bay 132kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 298 MW are waiting to connect here (largest by capacity: battery storage, onshore wind + storage). Contracted dates run from 12 Dec 2029 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Rigifa BESS | FIELD RIGIFA LIMITED | Battery storage | 200 | 12 Dec 2029 | Medium | 12 Dec 2029 | Scoping | 1 |
| Quintfall Forest Hybrid Wind and BESS 1 | VOLTALIA UK LTD | Onshore wind + storage | 98 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Redmoss Primary | SSEN Distribution | 1.8 km | 0 MW | 0 MW |
| Redmoss GSP | SSEN Distribution | 1.9 km | ||
| Kincorth Primary | SSEN Distribution | 3.1 km | 0 MW | 0 MW |
| Craiginches Primary | SSEN Distribution | 4.0 km | 0 MW | 0 MW |
| Ruthrieston Primary | SSEN Distribution | 4.3 km | 0 MW | 3.6 MW |
| Clayhills GSP | SSEN Distribution | 5.3 km |
Thinking of connecting near Gills Bay 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New East Coast 400kV: 1,000 MW waiting
- Redmoss: 20 MW waiting
- Persley 132/33kV GSP: 50 MW waiting
- Hurlie 400kV substation: 3,408 MW waiting
- Womblehill BESS Farm 132kV: 200 MW waiting