Persley 132/33kV GSP: grid connection queue
Persley 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jul 2026 to 30 Jul 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Persley Croft BESS | Persley Croft BESS Ltd | Battery storage | 50 | 30 Jul 2026 | n/a | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 18 Aug 2026 | Persley Croft BESS | 31 Oct 2026 | 31 Jul 2026 | -3 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Whitestripes Primary | SSEN Distribution | 0.9 km | 15 MW | 2.3 MW |
| Persley GSP | SSEN Distribution | 2.0 km | ||
| Haudagain Primary | SSEN Distribution | 2.3 km | 19 MW | 10 MW |
| Bridge of Don Primary | SSEN Distribution | 2.4 km | 12 MW | 5.1 MW |
| Hayton Primary | SSEN Distribution | 2.5 km | 19 MW | 19 MW |
| Stoneywood (T1 & T2) Primary | SSEN Distribution | 2.7 km | 22 MW | 14 MW |
Thinking of connecting near Persley 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New East Coast 400kV: 1,000 MW waiting
- Gills Bay 132kV: 298 MW waiting
- Dyce 132/33kV: 66 MW waiting
- Dyce 132/33kV: 30 MW waiting
- Womblehill BESS Farm 132kV: 200 MW waiting