Womblehill BESS Farm 132kV: grid connection queue

Womblehill BESS Farm 132kV · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Dec 2029 to 31 Dec 2029.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Womblehill BESS FarmRE Projects Development LimitedBattery storage20031 Dec 2029Medium31 Dec 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Kintore GSPSSEN Distribution1.1 km
Torryburn PrimarySSEN Distribution1.8 km0 MW0 MW
Kemnay PrimarySSEN Distribution5.6 km0 MW11 MW
Inverurie PrimarySSEN Distribution7.9 km0 MW12 MW
Skene PrimarySSEN Distribution8.7 km0 MW13 MW
Harvest Avenue PrimarySSEN Distribution9.2 km0 MW20 MW

Thinking of connecting near Womblehill BESS Farm 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points