Womblehill BESS Farm 132kV: grid connection queue
Womblehill BESS Farm 132kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Dec 2029 to 31 Dec 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Womblehill BESS Farm | RE Projects Development Limited | Battery storage | 200 | 31 Dec 2029 | Medium | 31 Dec 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kintore GSP | SSEN Distribution | 1.1 km | ||
| Torryburn Primary | SSEN Distribution | 1.8 km | 0 MW | 0 MW |
| Kemnay Primary | SSEN Distribution | 5.6 km | 0 MW | 11 MW |
| Inverurie Primary | SSEN Distribution | 7.9 km | 0 MW | 12 MW |
| Skene Primary | SSEN Distribution | 8.7 km | 0 MW | 13 MW |
| Harvest Avenue Primary | SSEN Distribution | 9.2 km | 0 MW | 20 MW |
Thinking of connecting near Womblehill BESS Farm 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kintore: 1,840 MW waiting
- Kintore 275kV: 300 MW waiting
- NEW FETTERESSO 132KV SUBSTATION: 112 MW waiting
- Fetteresso 132kV substation: 105 MW waiting
- Fetteresso: 50 MW waiting