Fetteresso 132kV substation: grid connection queue
Fetteresso 132kV substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 105 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Fasque Windfarm | ScottishPower Renewables (UK) Limited | Mixed and other | 105 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kemnay Primary | SSEN Distribution | 4.1 km | 0 MW | 11 MW |
| Kintore GSP | SSEN Distribution | 4.4 km | ||
| Torryburn Primary | SSEN Distribution | 6.8 km | 0 MW | 0 MW |
| Midmar Primary | SSEN Distribution | 7.5 km | 0 MW | 3.1 MW |
| Inverurie Primary | SSEN Distribution | 9.3 km | 0 MW | 12 MW |
| Skene Primary | SSEN Distribution | 11.1 km | 0 MW | 13 MW |
Thinking of connecting near Fetteresso 132kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kintore: 1,840 MW waiting
- Kintore 275kV: 300 MW waiting
- NEW FETTERESSO 132KV SUBSTATION: 112 MW waiting
- Fetteresso: 50 MW waiting
- Fetteresso 132/33kV GSP: 42 MW waiting