Benzene

NEW FETTERESSO 132KV SUBSTATION: grid connection queue

NEW FETTERESSO 132KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 112 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
112 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Colmealie Wind - Solar - BESS FarmGalileo 21 LimitedMixed and other11231 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Kemnay PrimarySSEN Distribution4.1 km0 MW11 MW
Kintore GSPSSEN Distribution4.4 km
Torryburn PrimarySSEN Distribution6.8 km0 MW0 MW
Midmar PrimarySSEN Distribution7.5 km0 MW3.1 MW
Inverurie PrimarySSEN Distribution9.3 km0 MW12 MW
Skene PrimarySSEN Distribution11.1 km0 MW13 MW

Thinking of connecting near NEW FETTERESSO 132KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points