Fetteresso 132/33kV GSP: grid connection queue
Fetteresso 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 42 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Craigneil Wind Farm | ESB ASSET DEVELOPMENT UK LIMITED | Onshore wind | 42 | 31 Oct 2030 | High | 16 Sep 2032 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kemnay Primary | SSEN Distribution | 4.1 km | 0 MW | 11 MW |
| Kintore GSP | SSEN Distribution | 4.4 km | ||
| Torryburn Primary | SSEN Distribution | 6.8 km | 0 MW | 0 MW |
| Midmar Primary | SSEN Distribution | 7.5 km | 0 MW | 3.1 MW |
| Inverurie Primary | SSEN Distribution | 9.3 km | 0 MW | 12 MW |
| Skene Primary | SSEN Distribution | 11.1 km | 0 MW | 13 MW |
Thinking of connecting near Fetteresso 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kintore: 1,840 MW waiting
- Kintore 275kV: 300 MW waiting
- NEW FETTERESSO 132KV SUBSTATION: 112 MW waiting
- Fetteresso 132kV substation: 105 MW waiting
- Fetteresso: 50 MW waiting