Kintore: grid connection queue

Kintore GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 1,840 MW are waiting to connect here (largest by capacity: offshore wind, mixed and other). Contracted dates run from 31 Oct 2029 to 30 Jun 2037.

2projects in the queue
1,840 MWwaiting to connect
0 MWalready connected
40 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Thainstone Energy ParkAGILE ENERGY RECOVERY (INVERURIE) LIMITEDMixed and other4031 Oct 2029Medium31 Oct 2029Consents Approved2
North-East Offshore Hybrid AssetNational Grid Interconnector Holdings LimitedOffshore wind1,80030 Jun 2037Low30 Jun 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Kemnay PrimarySSEN Distribution4.1 km0 MW11 MW
Kintore GSPSSEN Distribution4.4 km
Torryburn PrimarySSEN Distribution6.8 km0 MW0 MW
Midmar PrimarySSEN Distribution7.5 km0 MW3.1 MW
Inverurie PrimarySSEN Distribution9.3 km0 MW12 MW
Skene PrimarySSEN Distribution11.1 km0 MW13 MW

Thinking of connecting near Kintore?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.