Dyce 132/33kV: grid connection queue

Dyce 132/33kV GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 66 MW are waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Apr 2025 to 31 Oct 2028.

2projects in the queue
66 MWwaiting to connect
0 MWalready connected
66 MWholding Gate 2
1date moves since 2 Jun 2026
45 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kincraig Energy CentreKINCRAIG ENERGY CENTRE LIMITEDSolar + storage2130 Apr 2025n/aUnder Construction/Commissioning2
PerwinnesPERWINNES SOLAR AND BATTERY STORAGE LIMITEDSolar + storage4531 Oct 2028High31 Oct 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
30 Jun 2026Kincraig Energy Centre30 Apr 202630 Apr 2025-12 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Ellon PrimarySSEN Distribution5.9 km0 MW0 MW
Kingseat PrimarySSEN Distribution6.2 km0 MW1.3 MW
Balmedie PrimarySSEN Distribution6.2 km0 MW8.8 MW
Dyce GSPSSEN Distribution11.6 km
Oldmeldrum PrimarySSEN Distribution12.1 km0 MW0 MW
Dyce North PrimarySSEN Distribution12.6 km0 MW10 MW

Thinking of connecting near Dyce 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points