Kinmuck BESS 132kV: grid connection queue

Kinmuck BESS 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 105 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 May 2027 to 31 May 2027.

1project in the queue
105 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
105 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kinmuck PV and BESS StationKINMUCK ENERGY STORAGE LIMITEDSolar + storage10531 May 2027High30 May 2029Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Hatton PrimarySSEN Distribution6.9 km0 MW0 MW
Ellon PrimarySSEN Distribution7.4 km0 MW0 MW
Stoneyhill PrimarySSEN Distribution9.5 km0 MW3.8 MW
Mintlaw PrimarySSEN Distribution12.5 km0 MW0 MW
Maud PrimarySSEN Distribution13.4 km0 MW0 MW
Peterhead Shell GSPSSEN Distribution14.0 km

Thinking of connecting near Kinmuck BESS 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points