Longside 400kV: grid connection queue
Longside 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
5 projects with 5,500 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Marram Wind Offshore Wind Farm | Marramwind Limited | Offshore wind | 3,000 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
| Muir Mhor Offshore Wind Farm | MUIR MHÒR OFFSHORE WIND FARM LIMITED | Offshore wind | 1,000 | 31 Oct 2033 | Low | 31 Oct 2033 | Awaiting Consents | none |
| Broadshore Offshore Wind Farm | Broadshore Offshore Wind Farm Limited | Offshore wind | 900 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
| Netherton BESS | HARMONY ENERGY LIMITED | Battery storage | 400 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| Netherton Hub Bess | Field Netherton Ltd | Battery storage | 200 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Netherton Hub Bess | 31 Oct 2035 | 31 Oct 2033 | -24 months |
| 13 Oct 2026 | Netherton Hub Bess | 31 Oct 2033 | 31 Oct 2035 | +24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Mintlaw Primary | SSEN Distribution | 3.1 km | 0 MW | 0 MW |
| Stoneyhill Primary | SSEN Distribution | 7.4 km | 0 MW | 3.8 MW |
| Peterhead Grange GSP | SSEN Distribution | 8.1 km | ||
| Peterhead Grange Primary | SSEN Distribution | 8.1 km | 0 MW | 0 MW |
| St Fergus GSP | SSEN Distribution | 8.3 km | ||
| Peterhead Shell GSP | SSEN Distribution | 9.5 km |
Thinking of connecting near Longside 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Longside 132kV: 200 MW waiting
- Peterhead Grange: 50 MW waiting
- ST FERGUS 132KV SWITCHING STATION: 100 MW waiting
- St Fergus: 100 MW waiting
- Peterhead 275kV: 910 MW waiting