St Fergus: grid connection queue
St Fergus · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| St Fergus | IB VOGT UK LTD | Solar + storage | 100 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| St Fergus GSP | SSEN Distribution | 1.8 km | ||
| Peterhead Grange GSP | SSEN Distribution | 6.1 km | ||
| Peterhead Grange Primary | SSEN Distribution | 6.1 km | 0 MW | 0 MW |
| Peterhead North Street Primary | SSEN Distribution | 7.0 km | 0 MW | 0 MW |
| Mintlaw Primary | SSEN Distribution | 9.3 km | 0 MW | 0 MW |
| Peterhead Shell GSP | SSEN Distribution | 9.8 km |
Thinking of connecting near St Fergus?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- ST FERGUS 132KV SWITCHING STATION: 100 MW waiting
- Peterhead Grange: 50 MW waiting
- Longside 400kV: 5,500 MW waiting
- Longside 132kV: 200 MW waiting
- Peterhead 275kV: 910 MW waiting