Redmoss: grid connection queue
Redmoss GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 20 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kincorth BESS | KINCORTH ENERGY STORAGE SYSTEM LTD | Battery storage | 20 | 31 Oct 2031 | Medium | 31 Oct 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Newtonhill Primary | SSEN Distribution | 2.5 km | 0 MW | 0 MW |
| Redmoss Primary | SSEN Distribution | 7.3 km | 0 MW | 0 MW |
| Redmoss GSP | SSEN Distribution | 7.3 km | ||
| Craigton Primary | SSEN Distribution | 7.3 km | 0 MW | 3.6 MW |
| Culter Primary | SSEN Distribution | 7.7 km | 0 MW | 3.6 MW |
| Ruthrieston Primary | SSEN Distribution | 8.2 km | 0 MW | 3.6 MW |
Thinking of connecting near Redmoss?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Gills Bay 132kV: 298 MW waiting
- New East Coast 400kV: 1,000 MW waiting
- Hurlie 400kV substation: 3,408 MW waiting
- Persley 132/33kV GSP: 50 MW waiting
- Womblehill BESS Farm 132kV: 200 MW waiting