Pembroke 400kV: grid connection queue

Pembroke 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 1,250 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2031.

5projects in the queue
1,250 MWwaiting to connect
2,199 MWalready connected
350 MWholding Gate 2
0date moves since 2 Jun 2026
300 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Llŷr Floating WindLlŷr Floating Wind LimitedOffshore wind20031 Oct 2028High15 Nov 2030Scopingnone
Pembroke BESS and Solar StationRenesola Hercules Energy 1 LimitedSolar + storage10031 Oct 2028High31 Oct 2030Awaiting Consentsnone
Pembroke BESSRWE Generation UK PlcBattery storage3507 Mar 2029Medium7 Mar 2029Consents Approved2
Llywelyn Floating Offshore Wind FarmRenantis UK LimitedOffshore wind30031 Mar 2029Medium31 Mar 2029Scoping1
Valorous Offshore Wind FarmBlue Gem Wind LimitedOffshore wind30031 Oct 2031Medium31 Oct 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Pembroke 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points