Llanteg 400kV: grid connection queue
Llanteg 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 700 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 15 Sep 2037 to 15 Sep 2037.
1project in the queue
700 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| ER TWD Energy | ER PROJECT DEVELOPMENT CO LIMITED | Onshore wind + storage | 700 | 15 Sep 2037 | Low | 15 Sep 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Llanteg 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Pembroke 400kV: 1,250 MW waiting
- Pembroke 132kV: 215 MW waiting
- South Wales West Connection Node B 400kV: 700 MW waiting
- South Wales West Connection Node C 400kV: 288 MW waiting
- SOUTH WALES WEST CONNECTION NODE A 132KV: 150 MW waiting