Pembroke 132kV: grid connection queue
Pembroke 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 215 MW are waiting to connect here (largest by capacity: battery storage, offshore wind). Contracted dates run from 26 Jul 2028 to 30 Jul 2028.
2projects in the queue
215 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
215 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Erebus | Blue Gem Wind Limited | Offshore wind | 95 | 26 Jul 2028 | High | 10 Aug 2030 | Scoping | none |
| Pembroke (spare bay) | Pembroke Green Limited | Battery storage | 120 | 30 Jul 2028 | High | 30 Jul 2030 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Pembroke 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Pembroke 400kV: 1,250 MW waiting
- Llanteg 400kV: 700 MW waiting
- South Wales West Connection Node B 400kV: 700 MW waiting
- South Wales West Connection Node C 400kV: 288 MW waiting
- Swansea North 400kV: 2,021 MW waiting